As part of the early-stage work for the Milsom Quarter Public Realm project, Drainage Surveys and Cleaning Maintenances will be carried out across a number of city centre streets during 4-8 August 2025.
To safely complete these surveys, temporary night-time road closures will be in place between 20:00 and 05:00 on selected dates. All streets will remain open during the day, and pedestrian access to homes and businesses will be maintained throughout.
Drainage Surveys are non-invasive, do not involve digging or noisy construction, and are designed to map underground utilities with minimal disruption.
Road closures map - click to enlarge
| Table of closures | Between the hours of 22.00 – 5.00 on only across each of the below periods |
||
| Area on Map | Road Closure | Start Date | End Date |
| 1 | Old King Street | 04/08/2025 | 05/08/2025 |
| 1 | John Street | 04/08/2025 | 05/08/2025 |
| 2a | Queen Square | 04/08/2025 | 05/08/2025 |
| 2b | Wood Street | 04/08/2025 | 05/08/2025 |
| 2b | Quiet Street | 04/08/2025 | 05/08/2025 |
| 3a | Milsom Street | 05/08/2025 | 06/08/2025 |
| 3b | New Bond Street | 05/08/2025 | 06/08/2025 |
| 4 | Green Street | 05/08/2025 | 06/08/2025 |
| 5 | Broad Street | 06/08/2025 | 07/08/2025 |
| 6 | Saracen Street | 06/08/2025 | 07/08/2025 |
| 7a | Walcot Street | 07/08/2025 | 08/08/2025 |
| 7b | Northgate Street | 07/08/2025 | 08/08/2025 |